Installing a rubber expansion joint correctly comes down to three things: flange alignment within 1/8 inch, the right bolt tightening sequence, and torquing to the correct spec for your flange type. Skip any of these and you risk premature seal failure or a joint that never seats properly. This guide walks through pre-installation checks, the bolt-up sequence, and torque requirements by flange configuration.

Pre-Installation Checklist

  • Confirm system operating requirements
    • Pressure rating / vacuum
    • Temperature
    • Vibration
    • Movements
  • Review anchors, supports, and alignment guides
    • Confirm anchors and guides can support thrust and spring rates
    • Add control units and compression sleeves if needed
  • Examine expansion joint for gouges and cuts
  • Remove all foreign material and debris
  • Replace any components found to be defective

Aligning and Positioning the Expansion Joint

To begin the process of installation, position pipe flange faces assuring axes are aligned within 1/8 inch. If excessive force is required to achieve this alignment, use of an offset expansion joint may be necessary. A thin layer of a non-petroleum-based lubricant, such as soapy water, may be used to help slide the expansion joint into place. Maintain proper support of the expansion joint as it is carefully moved into position and bolt holes are aligned. Do not remove the support until the expansion joint is fully bolted into place.

Bolt Installation and Torque Sequence

Once the rubber expansion joint is in position you can begin the installation of the bolts.

Step 1 – Insert bolts with washers through the retaining rings on the arched side of the expansion joint and then through the matting flange in a cross pattern.

Step 2 – Attach and hand tighten nuts with washers

Step 3 – Torque each bolt with the cross-bolt pattern until the outside edge bulges slightly

When control units are required, the gusset plates will be installed on the outboard side of the matting flange. The rods are inserted through the hole in the gusset place.

Torque requirements:

Tighten bolts in two to three successive steps in a cross-bolt pattern to the nominal torque in the table below. Periodically re-tighten the bolts after system start-up.

Full Faced Elastomer Flanges
2021 07 15 08 39 44 Window
Joints with Beaded Ends Torque Requirements
2021 07 15 08 40 00 Window

Post-Installation Inspection

Periodically inspect your expansion joint to confirm satisfactory installation and operation. Re-tighten bolts periodically to ensure proper seal. When welding near expansion joint, cover with blanket or protective device to prevent damage. Prior to installation, store the expansion joint in a dry, dark, cool warehouse flange down on a level surface.